SBL-BPR-00535: An error has occurred while initializing task '%1'.

Applies to:

Error Message Area:Business Processes/Workflow - BPR


Version:Siebel 8.0


Purpose

This document is intended to provide cause and corrective action information about Siebel Error Message SBL-BPR-00535: An error has occurred while initializing task '%1'.


Scope

This document is informational and intended for any user.


SBL-BPR-00535: An error has occurred while initializing task '%1'.

Explanation

Task controller failed to initialize the task due to some error.


Corrective Action

Please refer to lower level error messages for more detailed explanation and correction actions.