SBL-BPR-00506: This operation cannot be performed until the task controller has initialized a new task instance.

Applies to:

Error Message Area:Business Processes/Workflow - BPR


Version:Siebel 8.0


Purpose

This document is intended to provide cause and corrective action information about Siebel Error Message SBL-BPR-00506: This operation cannot be performed until the task controller has initialized a new task instance. The current task instance has either been completed, paused or canceled.


Scope

This document is informational and intended for any user.


SBL-BPR-00506: This operation cannot be performed until the task controller has initialized a new task instance. The current task instance has either been completed, paused or canceled.

Explanation

This operation should be performed on an initialized task. However, the task controller has not been initialized with a task yet. The current task has either been completed, paused or canceled.


Corrective Action

Please initialize a task before performing this operation.






תגובות

פוסטים פופולריים מהבלוג הזה

Profile Attributes and Open UI

SBL-BPR-00191: The rowId of the active row of the primary buscomp '%1', '%2', does not match the Primary Id

SBL-SVC-00150